07 / DIAGNOSTIC LOGICIT company / distributed offices

IT company / distributed offices

Projects look almost finished — yet keep arriving late

Problem

Low management visibility, missed project deadlines, and a growing volume of work stuck at “80% complete.” More meetings and additional project managers do not restore predictability.

01 / Common assumption

The issue is attributed to weak remote-work discipline, time-zone differences, or insufficient communication between offices.

02 / What the diagnostic revealed

A flow map — task → development → review → integration → acceptance → release — revealed that work accumulated not in development, but in technical approval and integration. AI had accelerated code production without accelerating architecture, security, compatibility, or client-acceptance decisions. Every non-standard decision depended on two senior specialists, while time zones left only one short approval window per day.

03 / Core constraint

The throughput of technical approval, code review, and acceptance — not coding speed or the number of project managers.

04 / COFB

COFB intervention scenario

  1. 01

    Limit work in progress and make the approval queue visible to every team.

  2. 02

    Create a daily decision-overlap window across time zones and a standard decision packet: context, options, risks, and recommendation.

  3. 03

    Do not start more work than the system can review, integrate, and accept within the current cycle.

  4. 04

    Delegate routine decisions to certified reviewers in each time zone; reserve senior specialists for exceptions.

  5. 05

    Automate routine checks while keeping non-standard architecture and client decisions under expert control.

05 / How to verify the hypothesis

Age of the technical queue, time from development complete to release, rework rate, and the percentage of projects delivered on time without adding meetings.